Final roof pour on the Casa Finance City tower

Site12.11.2026By Works management4 min read

Thirty-four months after the first earthworks, the 21-level frame is complete, two weeks ahead of schedule.

On the morning of 12 November, the concrete pump filled the last slab of the Casa Finance City office tower. Thirty-four months after the first excavation, the 21-level frame is complete, two weeks before the contract date.

There was nothing spectacular about this last pour, and that is exactly what we were after: 186 m³ poured in seven hours, checked by the lab, without a minute's stop.

An eight-day cycle held for sixteen floors

The core was built with climbing formwork, the floors with modular traditional formwork. From the fifth level, the team held an eight-day cycle per floor: two days of formwork, two of rebar, one of openings, one of pouring and two of striking and preparation.

Rebar arrived prefabricated at night, just in time: on a plot with no storage area, every delivery was planned to the hour.

A fast site is first of all a site where nobody waits for anybody.

Next: facades and finishing trades

The glazed facades follow the frame, ten levels behind. The technical trades take over the floors as they are released. Handover to the client remains set for the third quarter of 2027.

  • 34months of structural works
  • 186 m³for the last slab
  • 0lost-time accidents