The project
Two civil structures totalling 640 linear metres, built under traffic on the urban motorway.
The challenge
Keeping 90,000 vehicles a day moving, placing 64 precast beams above the lanes and holding 24 months despite two rainy seasons.
Our answer
Beams precast on a dedicated yard, night lifts in four-hour windows with two mobile cranes, falsework designed in house and approved by the inspection body.
The site in pictures


The results
- 640 mlof structures
- 64beams placed at night
- 0unplanned closures