The project
A 21,000 m² food-processing plant delivered all trades in thirteen months.
The challenge
Food-hygiene requirements (floors, walls, falls), production lines delivered by the manufacturer on a fixed date and process networks to integrate in the structure.
Our answer
Hygiene zoning set from the sketch, resin floors and insulated panels installed as a clean room, and process openings coordinated with the line supplier.
The site in pictures


The results
- 13 moisall trades
- 21 000 m²covered
- J−10lines installed early