Industrial · Zenata

Logistics hub

Client
Private logistics property company
Amount
MAD 186 M excl. VAT
Duration
16 months
Lot
Single lot · All trades
Area
52,000 m²
Year
2023

The project

A 52,000 m² logistics hub delivered all trades in sixteen months, docks and sprinklers included.

The challenge

A 50,000 m² slab without saw-cut joints for high-bay storage, on clay soil, with an opening date fixed before the operator had finished its studies.

Our answer

Soil replacement and controlled compaction, a fibre slab poured in 2,000 m² strips with laser screeds, the steel frame erected zone by zone right after foundations and sprinkler networks prefabricated in the workshop.

The site in pictures

The results

  • 16 moisfrom excavation to docks
  • ±3 mmflatness over 2 m
  • 48docks with levellers