The project
A 52,000 m² logistics hub delivered all trades in sixteen months, docks and sprinklers included.
The challenge
A 50,000 m² slab without saw-cut joints for high-bay storage, on clay soil, with an opening date fixed before the operator had finished its studies.
Our answer
Soil replacement and controlled compaction, a fibre slab poured in 2,000 m² strips with laser screeds, the steel frame erected zone by zone right after foundations and sprinkler networks prefabricated in the workshop.
The site in pictures


The results
- 16 moisfrom excavation to docks
- ±3 mmflatness over 2 m
- 48docks with levellers