The project
The roads, utilities and landscape of a 240-home residence on 6.4 hectares, delivered in eleven months.
The challenge
Working between buildings being finished, without cutting other trades' access, with connections depending on three utility companies.
Our answer
Phasing by block, shared trenches for dry networks, temporary gravel roads then asphalt at the end, and a coordinator dedicated to the utility companies.
The site in pictures


The results
- 11 moisfor 6.4 ha
- 7,2 kmof networks
- 420trees planted